The Roseville Parkway Extension Project is now open and includes:
- Four lane roadway between Washington and just west of Foothills Boulevard (two lanes in each direction);
- Bridge over Industrial Avenue and Union Pacific railroad tracks;
- Landscaping;
- Sidewalk;
- Class II bike lanes; and
- Multi-use path.
Project rendering
Construction update 2024:
2020 - 2022 |
Engineering and environmental study phase |
July 23 – August 6, 2020 |
Virtual public open house |
October 2023 - 2025 |
Construction phase |
January 29, 2025 |
Open to the public |
Timelines are approximate and subject to change. Public comment period: 20 days from July 24 - August 13, 2020.
Copies of the Initial Study/Mitigated Negative Declaration are available for public review.
Final Notice of Intent to adopt Mitigated Negative Declaration
Roseville Parkway Extension Project Initial Study/Mitigated Negative Declaration
Appendices
Documents can be viewed in person by appointment, at the City of Roseville Permit Center, 311 Vernon Street, Roseville, CA 95678. To schedule an appointment online:
roseville.ca.us/DS-appointment or call (916) 774-5285.
Written comments on the adequacy of the Mitigated Negative Declaration must be received no later than 5:00 p.m. on August 13, 2020. During the public review period written comments may be provided to:
Terri Shirhall, Environmental Coordinator
Development Services Department
City of Roseville
311 Vernon Street
Roseville, CA 95678
(916) 774-5536
EmailFrom July 23 – August 6, 2020, a Virtual Open House was held to introduce and build awareness of the project. More than 50 community members provided public comments or questions, and more than 1,500 people viewed the informational project video and website during the Virtual Open House.
Learn more about how the improvements will provide better connectivity by watching the virtual community presentation.
View the 2020 virtual open house summary.
Project costs were approximately $26,000,000. Funding came entirely from developer-paid Traffic Mitigation Fees.
No City General Fund or Measure B money contributed to this project.
Learn more about how Roseville plans for growth and development:
roseville.ca.us/DevelopmentDecoded.
Be notified of project updates.
Subscribe to our email newsletter and follow us on
social media.